Canadian company Northland Power raised its adjusted EBITDA by 9% between July and September 2026. Its offshore wind farms Hai Long and Baltic Power have all their turbines installed.
The adjusted EBITDA of Northland Power reached CAD 279.6 million between July and September 2026, compared to CAD 257 million in the same period of 2025. According to inspenet.com, the company also completed the installation of the turbines for its offshore wind farms Hai Long and Baltic Power and commenced commercial operation of the Jurassic BESS storage project in Alberta.
Revenue from energy sales rose to CAD 564.6 million, up from CAD 557.6 million the previous year. Cash generated from operations was CAD 381.5 million, compared to CAD 325.1 million in Q3 2025.
The net profit was CAD 201.1 million, compared to a loss of CAD 455.8 million a year earlier. The company explains this difference due to a non-cash accounting impairment of CAD 526.5 million recorded in 2025.
Despite this, free cash flow per share fell to USD 0.06, down from USD 0.17. The company attributes the decline to lower operating results, reduced revenues before the completion of Hai Long and Baltic Power, and financial costs, debt payments, and taxes.
In Taiwan, the Hai Long wind farm, with 1 GW capacity, completed the installation of its 73 turbines. The company expects to obtain final approvals in the first half of 2027 and keeps costs within initial estimates.
In Poland, the Baltic Power wind farm, with 1.1 GW capacity, has installed its 76 turbines, and over 70% are already generating electricity. Northland expects to complete commissioning in Q4 2026. Together, both projects contributed CAD 35 million to the increase in adjusted EBITDA.
In Canada, Jurassic BESS has a capacity of 80 MW and 160 MWh. According to the company, it started operating ahead of schedule and below the initial budget. Additionally, the solar project in Alberta that was under development has become Midnight Alberta BESS, with 200 MW and 800 MWh.
In Poland, Northland is constructing the Kamionka and Mieczysławów battery systems, which total 300 MW and 1.2 GWh. To finance them, the company has secured debt of approximately 500 million zlotys, equivalent to CAD 185 million. Kamionka is set to begin operations in early 2028 and Mieczysławów in mid-year.
The company is also developing new storage systems in the Netherlands and Spain. The operational availability reached 93% and Northland reaffirms its financial forecasts for 2026.